Welcome to QCFI Knowledge Test
Team name - Full Name of Leader
Email
Phone
Name of Company
1.
If maximum marks given for any checkpoint is’S’ Auditor in self audit has given 5 out of 5. What will be the role of sub zone! Zone leader?
A. To appreciate the people of that area
B. To go and visit the area with auditors to ensure the marks given is correct
C. Take out that point from the checklist
D. Inform the zone head for improvement of that area.
2.
Who was awarded the Deming prize in 1960 for his contribution in developing technique for industrial optimization?
A. Dr. Deming
B. Dr. A. V. Faignbaum
C. Dr. W. A. Shewhart
D. Dr. Genichi Taguchi
3.
Which outside agencies can be involved in 5’S implementation?
A. Contract Workers
B. Vendors and suppliers
C. Ancillary Agency
D. Bank Employees
4.
Name the concept which is a” study and application group” for learning, development and improvement.
A. Work Place Management
B. Quality Circle
C. Kaizen
D. Six Sigma
5.
While selecting a set of problem through ranking/priority ,what is to be done to ensure that the interest of all members to solve the problem does not get diminished?
A. Follow instruction of Supervisor
B. Follow instruction of Leaders
C. Follow the priority schedule of ranking
D. None of above
6.
One of the important features of a particular concept is Treating the “Next process as the customer” What is that concept?
A. CWQC
B. Six Sigma
C. SPC
D. QIT
7.
Lean is not about
A. Less Time
B. Less Inventory
C. Less space
D. Less Production
8.
How many Quality Circles, one Facilitator can guide?
A. One
B. Three
C. No limit but manageable
D. Five
9.
For establishing Total Quality Management in the organization, whose responsibility is to provide long term stability through building up the cadres down the line.
A. Top management
B. Co-ordinator
C. Facilitator
D. Politicians
10.
As per QCFI, number of checkpoints in self audit should be:
A. Minimum 30
B. Maximum 30
C. No maximum limit
D. No limit given
11.
If target date is over and action not taken, what to be done by the zone! sub zone leader?
A. Remind to the responsible person
B. Remind the responsible person and record the date of reminder in remark column
C. Follow point ‘B’ and after three reminders, report to Zone head
D. Report to Management
12.
Data obtained by count of defects, count of occurrences i.e. no. of accidents etc. can be termed as:
A. Attribute
B. Variable
C. Accidental
D. None of the above
13.
Is leadership of Quality Circle rotatable?
A. No
B. Yes
C. Facilitator
D. Depends on Management
14.
Name the Activity chart in which start and end dates are written below a reverse triangle
A. Mile Stone Chart
B. Gannt Chart
C. PERT Chart
D. None of above
15.
Who popularised the Scatter Diagram?
A. Dr. W. A. Shewhart
B. Dr. J.M. Juran
C. Dr. K. Ishikawa
D. Dr. Genuchi Taguchi
16.
The Coordinator is suppose to inform the auditor for ?
A. Marks give by the previous auditor
B. Comments given by the previous auditors zone / sub zone wise
C. Support given by Zone! Sub zone in previous audit
D. Non cooperative sub zones in 5-S audit in previous audit.
17.
Why labelling in items is important in 5’S?
A. To identify quickly
B. To retrive immediately
C. To know the kinds of item
D. All above
18.
The results of Trial implementation and regular implementation
A. May be same
B. May encounter some problems in regular implementation
C. May be alright in trial implementation
D. All above are possible
19.
What is the frequency of doing Seiri
A. Monthly
B. Six monthly
C. Periodically (as per management decision)
D. As per need
20.
Use of which tool/technique helps to improve planning capability?
A. Control Chart
B. Gantt Chart
C. Cause and effect diagram
D. Flow Chart
21.
What is the basic objective of Quality Circle?
A. To improve the image of the Organizations
B. To solve problem given by Facilitator
C. For self and mutual development
D. For members to work in Team
22.
JUSE, Japan has changed one important element in Dr. K. Ishikawa’s definition of Quality Circle, What is that specified?
A. Role of Quality Circle
B. Role of Executives and Managers
C. Role of QC Members
D. Combination of A & B
23.
During self audit, auditor should carry for giving marks.
A. Audit Register
B. Check Points and Rough audit sheet
C. Rough Audit sheet
D. Rough audit sheet and Camera
24.
In priority/rating method, in case of tie up scores between two projects, how to select problem?
A. Leader score to be considered
B. Dy Leader score to be considered
C. Decision of Facilitator is the best option
D. Any of above
25.
For process control, what step should be taken just after analysing the variation?
A. Modify the process
B. Controlling the variation
C. Combination of A & B
D. None of the above
26.
Which one is not used for selection of problem?
A. Priority number
B. Ranking method
C. Pareto Analysis
D. Gantt Chart
27.
Whose responsibility is to check the reason if the circle is much behind schedule, as per their Milestone chart?
A. Deptt Head
B. Facilitator
C. Coordinator
D. Leader
28.
Utility of which of the elementary seven tools can be considered as responsible for the introduction of the New Seven Tools
A. Cause & Effect diagram
B. Control Chart
C. Scatter diagram
D. Histogram
29.
Who is the Certifying agency for 5’S implementation jointly with JUSE
A. Productivity Council of India
B. CII
C. QCFI
D. Safety council of India
30.
When process is under control which type of variation occurs?
A. Random
B. Abnormal
C. Continuous
D. Discontinuous
31.
Lean Quality Circle helps people for:
A. Self Development
B. Mutual Development
C. Sharing the knowledge
D. All the above
32.
A Quality Circle group made Pareto Diagram of accidents resulting in physical injuries (Finger, Eyes, Arms and legs). Name the Pareto
A. Accident
B. Phenomenon
C. Causes
D. Mistakes
33.
Due to which reason , variation in the dispersion of data occur within the limit of Quality Standards?
A. Chance causes
B. Assignable causes
C. Unforeseen causes
D. Common Causes
34.
Dr. Ishikawa renamed the study group as Quality Control Circle in
A. April 1960
B. April 1962
C. January 1962
D. November 1962
35.
As per Dr Juran, what to be added in evolutionary progress to achieve revolutionary progress?
A. Continuous Improvement
B. Continuous Training
C. Continuous Practice
D. Continuous Facilitation
36.
Out of 3 steps of Kaizen, one is Eliminate, other is Change, name the third one.
A. Exchange
B. Reduce
C. Removal
D. Exclusion
37.
In hich of the following area Kaizen can be implemented?
A. Social Life
B. Domestic Life
C. Working Life
D. All above
38.
5’S concepts is the Gate way of ---
A. Lean management
B. Total Productive Maintenance
C. Total Quality Management
D. All above
39.
As per Dr. Juran, for proper adoption of TQM important measures are
A. Operating procedure
B. Customer Satisfaction
C. Financial Performance
D. All the above
40.
Meetings of LQC helds :-
A. Weekly
B. As per Project Demand
C. As per Facilitator’s Instructions
D. Daily
41.
Out of following tools which one can be used for generating a list of problem?
A. Cause and Effect Diagram
B. Check Sheet
C. Scatter Diagram
D. None of the above
42.
In Lean Quality Circle, Minimum number of Members including the Facilitator will be
A. 3
B. 4
C. 5
D. 6
43.
Which technique maybe used by QC Team for selection of problem?
A. Gantt method
B. Ranking method
C. PERT method
D. Critical Path Method (CPM)
44.
What is not the strategy of Kaizen?
A. To eliminate waste
B. To eliminate process
C. To create short cut method
D. Continuous improvement
45.
During development of solution to the problems the responsibilities for actions within a time frame are assigned by:
A. Leader with the consensus of member
B. Facilitator with the consensus of member
C. One of the member
D. Coordinator with the consensus of member